600m³/day Cheese Factory Wastewater Treatment Project Case

1. Case Basic Information

Cheese Factory Wastewater Treatment

1.1 Project Subject

  • Provider: HELLA WATER, a trusted supplier of high-performance water treatment product, specializes in customized industrial wastewater treatment solutions for food processing industries.
  • Project Name: Tunisia 600 Tons/Day Cheese Production Wastewater Treatment Project
  • Core Objective: Treat high-concentration organic wastewater from cheese production to meet local discharge standards (DB 37/599-2006), realize energy recovery (biogas utilization), and minimize environmental impact.

1.2 Treatment Scale & Water Quality Parameters

Inlet Water Quality (Comprehensive Production Wastewater)

ParameterValue
CODcr21800 mg/L
BOD₅9600 mg/L
Suspended Solids (SS)1600 mg/L
Kjeldahl Nitrogen298 mg/L
Total Phosphorus164 mg/L
Oil250 mg/L
Detergent4.1 mg/L
pH3.2 (acidic)

Effluent Discharge Standard (Local Requirements)

ParameterValue
CODcr≤200 mg/L
BOD₅≤50 mg/L
SS≤50 mg/L
Kjeldahl Nitrogen≤5 mg/L
Total Phosphorus≤2 mg/L
Oil≤10 mg/L
Detergent≤1 mg/L
pH6.5-9.0

1.3 Core Equipment & Process Configuration

Process UnitKey EquipmentSpecificationsQuantity
PretreatmentMechanical Grille + Dissolved Air Flotation MachineHydraulic curved screen; PAM/PAC dosing device1 set (grille), 1 set (flotation machine)
Regulation & NeutralizationpH Adjustment Pool + Equalization TankSemi-underground steel-concrete structure; Effective volume: 200 m³1 set each
Anaerobic TreatmentUASB Anaerobic ReactorVolume: 180 m³; Volume load: 5-10 kgCOD/m³·d1 unit
Aerobic TreatmentMulti-stage A/O Reaction TankLevel I A/O: 1200 m³; Level II A/O: 500 m³; Tubular microporous aerator1 set
Solid-Liquid SeparationSecondary Sedimentation TankSurface load: 8 m³/m²·h; Total volume: 800 m³1 unit
Sludge TreatmentSpiral Dewatering Machine + Sludge ThickenerDYLT-301 type; PAM dosing device (JY-500)1 set each
Energy RecoveryBiogas Collection & Purification SystemDesulfurization tower + gas storage tank + flame arrester1 set
Automatic ControlPLC Control System + Online MonitorsDO, pH, level, flow rate monitors; Central control cabinet1 set

1.4 Design Standards & Compliance

The project adheres to industry core standards and regulations, including:

  • DB 37/599-2006: Local Wastewater Discharge Standard
  • GBJ 14-87 (1997 edition): Code for Design of Outdoor Drainage
  • GBJ 13-86: Outdoor Water Supply Design Code
  • GB 141-90: Code for Structural Design of Water Supply and Drainage Engineering
  • JB2932-1999: Technical Specifications for Water Treatment Equipment
  • ISO9001: Quality Management System Certification

1.5 Application Scenarios

  • High-concentration organic wastewater treatment in dairy/cheese factories
  • Food processing industry wastewater purification (containing proteins, fats, sugars)
  • Industrial wastewater treatment projects requiring energy recovery (biogas)
  • Acidic wastewater treatment with corrosion protection requirements
  • Compliance-oriented wastewater treatment in regions with strict discharge standards

2. Project Core Pain Points & Requirements

Cheese Factory Industrial Wastewater Treatment Project

2.1 Industry Common Pain Points

  1. High Pollution Load: Cheese wastewater is high-concentration organic wastewater (COD up to 21800 mg/L) with high nitrogen and phosphorus, leading to severe eutrophication if discharged directly.
  2. Acidic Corrosion: pH=3.2 acidic wastewater corrodes equipment and pipelines, requiring special anti-corrosion treatment.
  3. Ammonia Nitrogen Surge: Anaerobic treatment of protein-rich wastewater increases ammonia nitrogen concentration (200-600 mg/L), making denitrification difficult.
  4. Large Sludge Production: Traditional processes generate massive sludge, increasing disposal costs and secondary pollution risks.
  5. High Operating Costs: Aerobic treatment of high-concentration wastewater consumes excessive energy; lack of resource recovery leads to waste.

2.2 Customer Core Requirements

  • 达标排放: Efficiently remove COD, BOD, ammonia nitrogen, and phosphorus to meet local discharge standards.
  • Corrosion Resistance: Ensure equipment and structures withstand acidic wastewater and long-term stable operation.
  • Energy Recovery: Utilize biogas generated from anaerobic treatment to reduce energy consumption and operating costs.
  • Sludge Reduction: Minimize sludge production and simplify sludge disposal to lower environmental and economic burdens.
  • Intelligent Operation: Realize automatic control of pH, flow rate, and aeration to reduce manual intervention.

3. Hella Water Customized Solutions

Cheese Processing Plant Wastewater Treatment System

3.1 Process Design: Anaerobic-Aerobic Integration + Energy Recovery

The solution adopts a “Pretreatment → Regulation & Neutralization → UASB Anaerobic → Multi-stage A/O → Solid-Liquid Separation → Disinfection” integrated process, combined with biogas energy recovery:

  1. Pretreatment Stage:
    • Mechanical Grille: Removes large suspended solids (e.g., cheese residues, fibers) to protect subsequent equipment.
    • Dissolved Air Flotation Machine: Cooperates with chemical dosing system (PAM/PAC) to remove 85% of oil and 90% of SS, reducing the burden on biological treatment.
  2. Regulation & Neutralization Stage:
    • Equalization Tank: Balances water quality and quantity (retention time: 5h) to mitigate impact loads; adjusts pH by recycling effluent (no additional neutralizer needed during stable operation).
    • pH Adjustment Pool: Temporarily adjusts acidic wastewater during commissioning to ensure suitable conditions for anaerobic/aerobic microorganisms.
  3. Anaerobic Treatment Stage (Energy Recovery):
    • UASB Anaerobic Reactor: Degrades 60-70% of COD through hydrolysis, acidification, and methanogenesis; generates biogas (methane content ≥65%).
    • Biogas Utilization: Biogas is purified (desulfurization + dehydration) and used for boiler combustion, power generation, or factory canteen use, reducing energy costs by 30%.
  4. Aerobic Treatment Stage (Deep Purification):
    • Multi-stage A/O Reaction Tank:
      • Level I A/O: Denitrification with organic carbon sources in wastewater; reduces nitrate nitrogen to N₂.
      • Level II A/O: Nitrification (DO=2-3 mg/L) converts ammonia nitrogen to nitrate nitrogen; realizes deep denitrification and phosphorus removal.
      • Tubular microporous aerators ensure high oxygen transfer efficiency, reducing aeration energy consumption.
  5. Solid-Liquid Separation & Sludge Treatment:
    • Secondary Sedimentation Tank: Separates activated sludge from treated water; sludge reflux to A/O tank maintains microbial concentration.
    • Spiral Dewatering Machine: Dewaters excess sludge (moisture content ≤60%); granular sludge from UASB is sold as commercial inoculant, realizing resource utilization.

3.2 Core Technical Advantages

Technical HighlightDescription
High-Efficiency Anaerobic-Aerobic SynergyUASB removes most COD (energy-saving) + multi-stage A/O achieves deep denitrification; total COD removal rate ≥99%, ammonia nitrogen removal rate ≥98%.
Corrosion Protection DesignSteel-concrete structures with fiberglass lining; acid-resistant pumps/pipelines; adapts to pH=3.2 acidic wastewater.
Energy RecoveryBiogas generation (≈0.5 m³ biogas/kgCOD degraded) reduces energy consumption by 30-40% compared to traditional processes.
Sludge ReductionAnaerobic sludge production (0.05 kg/kgCOD) is 1/10 of aerobic processes; granular sludge recycling reduces disposal costs.
Intelligent ControlPLC automatic control of pH, flow rate, and aeration; online monitors (DO, pH, level) trigger alarms and adjust parameters in real time.

3.3 Key Supporting Systems

  • Pre treatment filtration system: Grille + flotation machine ensures inlet water quality for UASB and A/O systems.
  • Anti-corrosion System: Fiberglass lining for tanks, acid-resistant pipelines/pumps, and stainless steel components to extend service life.
  • Emergency Protection: Overflow pipes and accident tanks prevent untreated wastewater discharge during equipment failure.

4. Project Effectiveness Verification

4.1 Pollutant Removal Efficiency

PollutantInlet ConcentrationEffluent ConcentrationRemoval Rate
CODcr21800 mg/L≤200 mg/L≥99.1%
BOD₅9600 mg/L≤50 mg/L≥99.5%
SS1600 mg/L≤50 mg/L≥96.9%
Kjeldahl Nitrogen298 mg/L≤5 mg/L≥98.3%
Total Phosphorus164 mg/L≤2 mg/L≥98.8%
Oil250 mg/L≤10 mg/L≥96.0%

4.2 Operational Performance

  • Stability: Continuous operation for 8000 hours with stable effluent quality; adapts to ±30% flow fluctuations and ±25% COD concentration changes.
  • Energy Efficiency: Biogas generation ≈10,900 m³/d (based on 21800 mg/L COD); annual energy saving ≈360,000 kW·h, reducing operating costs by USD 36,000 (0.1 USD/kW·h).
  • Sludge Reduction: Annual sludge production ≤150 tons (moisture content 60%), 70% less than traditional aerobic processes.
  • Corrosion Resistance: No equipment corrosion reported after 2 years of operation; anti-corrosion components maintain good performance.

4.3 Economic & Environmental Benefits

  • Economic Benefits: Annual energy savings USD 36,000; sludge disposal cost reduction USD 20,000; granular sludge sales income USD 15,000; total annual economic benefit ≈USD 71,000.
  • Environmental Benefits: Annual reduction of COD emission by ≈7,900 tons; ammonia nitrogen emission by ≈107 tons; phosphorus emission by ≈60 tons; biogas utilization reduces greenhouse gas (methane) emission.

5. Case Corresponding Product Quotation Description

5.1 Quotation Overview

ItemDescriptionTotal Amount (USD)
Core EquipmentUASB reactor, multi-stage A/O tank, flotation machine, sludge dewatering systemIncluded in total
Auxiliary SystemsBiogas purification system, automatic control system, online monitorsIncluded in total
Engineering Design & InstallationCivil construction design, equipment installation, pipeline connectionIncluded in total
Total Project Quotation–2,171,450

5.2 Quotation Terms

Term TypeDetails
Validity Period45 working days from the date of quotation
Payment TermsNegotiable (reference: 30% advance payment, 40% during construction, 30% after acceptance)
Project Cycle7 months (1 month design + 3 months civil construction + 2 months equipment installation + 1 month commissioning)
Warranty Period12 months from the date of acceptance (free repair/replacement for non-human damage)
IncotermsDAP (Delivered at Place, Tunisia)
Additional ServicesFree operator training (2-3 personnel); 24/7 online technical support

5.3 Additional Notes

  • The quotation includes equipment, design, installation, and commissioning; civil construction materials (steel, concrete) are excluded.
  • Spare parts (aerators, pumps, filters) are provided at 15% of the equipment price for long-term supply.
  • Biogas utilization system can be customized (power generation/boiler combustion) based on factory needs.

6. Frequently Asked Questions (FAQ)

6.1 Installation & Commissioning

Q: What are the on-site installation requirements for the UASB reactor?

A: The UASB reactor requires a flat foundation with load-bearing ≥5 tons/m²; installation space ≥10m×6m×8m (length×width×height). It needs to be connected to biogas storage and purification facilities; we provide detailed installation drawings and dispatch 2-3 engineers for on-site guidance. Commissioning takes 1 month, including granular sludge inoculation and system stabilization.

6.2 Maintenance & Upkeep

Q: How often does the UASB reactor and A/O tank require maintenance?

A: Routine maintenance includes: 1) UASB reactor: Check three-phase separator and water distributor every 3 months; desulfurize biogas system every 6 months. 2) A/O tank: Clean aerators every 6 months; replace worn aerator membranes every 2 years. 3) Sludge dewatering machine: Clean screw shaft every week; replace filter screen every 1 year.

Q: What is the service life of core equipment?

A: UASB reactor (15-20 years), multi-stage A/O tank (15 years), biogas purification system (10 years), sludge dewatering machine (8-10 years). We provide lifelong technical support and preferential spare parts supply.

6.3 Warranty & After-Sales

Q: What is covered under the 1-year warranty period?

A: Within the warranty period, we provide free repair or replacement for faults caused by design, manufacturing, or material defects, including core equipment (UASB reactor, A/O tank, control system), pumps, aerators, and monitors. Damage from improper operation, corrosion due to non-compliant water quality, or natural disasters is not covered.

Q: How to get after-sales technical support for overseas projects?

A: We provide 24/7 online support via email and video calls; for urgent on-site issues, technicians can be dispatched to Tunisia within 72 hours (additional fees apply for international travel). We also conduct semi-annual return visits to monitor system operation.

6.4 Operational Cost

Q: What is the estimated monthly operating cost of the system?

A: The main operating costs include electricity (aeration, pumps), chemicals (PAM/PAC), and labor. For a 600m³/d system, the monthly electricity cost is about USD 4,500 (excluding biogas energy savings), chemical cost about USD 1,200, and labor cost about USD 2,000. With biogas energy savings (≈USD 3,000/month), the net monthly operating cost is ≈USD 4,700.

6.5 Safety & Compliance

Q: Is biogas utilization safe, and how to prevent explosion risks?

A: Yes. The biogas system is equipped with desulfurization towers (removes H₂S), flame arresters, and pressure relief valves. The gas storage tank is installed in an open area ≥10m away from buildings; online biogas flow monitors trigger alarms for abnormal pressure. We provide safety training for operators to ensure compliant use.

Q: How to handle sudden increases in ammonia nitrogen concentration?

A: The multi-stage A/O system has strong shock resistance; the PLC control system automatically increases the nitrification liquid reflux ratio (up to 300%) and adjusts aeration intensity to enhance denitrification. If ammonia nitrogen exceeds 500 mg/L, the system activates emergency dosing of external carbon sources (e.g., methanol) to ensure effluent compliance.

Table of Contents

Share to

Latest Case
Scroll to Top
PURE WATER. BETTER BUSINESS.

Advanced water treatment solutionsbuilt for performance, reliabilityand sustainability.

High Efficiency RO Systems
Reliable Performance
Sustainable Solutions
Trusted by Industries Worldwide
Engineered for Quality & Durability
Expert Support From Start to Success
Get a Free Water Treatment Quote

Share your requirements and our experts will provide a tailored solution for your business.

PURE WATER. BETTER BUSINESS.

Advanced water treatment solutionsbuilt for performance, reliabilityand sustainability.

High Efficiency RO Systems
Reliable Performance
Sustainable Solutions
Trusted by Industries Worldwide
Engineered for Quality & Durability
Expert Support From Start to Success
Get a Free Water Treatment Quote

Share your requirements and our experts will provide a tailored solution for your business.