1. Case Basic Information

1.1 Project Subject
- Provider: HELLA WATER, a professional manufacturer of high-performance water treatment product, specializes in developing integrated electrocoagulation technology for efficient wastewater purification.
- Core Product: 500LPH Electrocoagulation Equipment (Model: BYECO-0.5)
- Project Objective: Achieve efficient removal of suspended solids, COD, chroma, and colloidal pollutants in wastewater through electrocoagulation technology, meeting discharge or reuse standards without chemical agents.
1.2 Equipment Specifications & Key Parameters
| Parameter | Specification |
|---|---|
| Model | BYECO-0.5 |
| Treatment Capacity | 0.5 m³/h (12 m³/d) |
| Equipment Dimensions | 2500mm × 1000mm × 1500mm |
| Equipment Weight | Estimated total weight: ≈1.2 tons |
| Material | Main body: Carbon steel (anti-corrosion treatment); Insulation board: High-molecular PE; Circuit connection plate: Copper plate; Electrode plate: Steel plate (4 m²) |
| Applicable Temperature | 0—90℃ |
| Inlet Water Pressure | 0.2 MPa |
| Inlet/Outlet Diameter | DN40 (both inlet and outlet) |
| Power Cabinet Dimensions | 600mm × 200mm × 500mm |
| Electrolysis Voltage | 0-12 V (adjustable) |
| Electrolysis Current | <1000A |
| Core Components | Rectifier for electroflocculation and flotation, slag scraping system, sludge discharge system, stainless steel electrical control box, aeration device (at the bottom of the electrolytic cell) |
1.3 Design Standards & Compliance
The equipment adheres to industry core standards and quality requirements, including:
- JB2932-1999: Technical Specifications for Water Treatment Equipment
- GB 8978-1996: Integrated Wastewater Discharge Standard
- ISO9001: Quality Management System Certification
- Safety standards for electrical control equipment (GB/T 3797-2005)
1.4 Application Scenarios
- Pre-treatment or deep treatment of industrial wastewater (printing and dyeing, electroplating, chemical, food processing wastewater)
- Purification of sewage treatment machine effluent to meet stricter discharge standards
- Removal of suspended solids, colloids, and chroma in low-to-medium concentration wastewater
- Water purification for small-scale agricultural irrigation or industrial reuse, aligning with pre treatment filtration system needs
2. Project Core Pain Points & Requirements

2.1 Industry Common Pain Points
- Chemical Agent Pollution: Traditional coagulation processes rely on PAC/PAM, leading to excessive sludge production, high disposal costs, and potential secondary pollution.
- Low Removal Efficiency: Conventional equipment struggles to remove fine colloids and stable chroma, resulting in unqualified effluent.
- High Maintenance Costs: Easily clogged filters and frequent sludge cleaning increase labor and material consumption.
- Complex Operation: Manual control of chemical dosing and sludge discharge requires professional operators, increasing management difficulty.
2.2 Customer Core Requirements
- Agent-Free Purification: Achieve efficient pollutant removal without adding chemical coagulants, reducing sludge production and environmental impact.
- High Treatment Efficiency: Remove ≥95% of suspended solids (SS), ≥70% of COD, and ≥90% of chroma to meet national discharge standards.
- Simple Operation & Maintenance: Integrate electrocoagulation, flotation, and sludge discharge functions; realize automatic operation to reduce manual intervention.
- Compact & Durable: Small footprint (≤5 m²) to fit small-scale workshops; anti-corrosion design ensures long service life.
- Cost Control: Low energy consumption and maintenance costs; no frequent replacement of core components.
3. Hella Water Customized Solutions

3.1 Process Design: Integrated Electrocoagulation-Flotation-Sedimentation Technology
The solution adopts a “electrocoagulation → in-situ flotation → sludge separation” integrated process, realizing agent-free wastewater purification:
- Electrocoagulation Stage:
- Steel electrode plates generate metal hydroxides (coagulants) through electrolysis, which adsorb and aggregate suspended solids, colloids, and organic pollutants in wastewater.
- Adjustable voltage (0-12V) and current (<1000A) adapt to different water quality conditions, ensuring stable treatment effects.
- Flotation & Sedimentation Stage:
- Bottom aeration device generates micro-bubbles, which adhere to flocculated pollutants and float to the water surface.
- Top slag scraping system automatically removes floating sludge; bottom sludge collecting bucket and discharge system realize continuous sludge separation, avoiding equipment clogging.
- Integrated Control:
- Stainless steel electrical control box integrates rectifier and operation switches, simplifying parameter adjustment and equipment start-stop control.
- Compact design (2500×1000×1500mm) integrates all functions, reducing installation space to ≤5 m².
3.2 Core Technical Advantages
| System Module | Technical Highlights |
|---|---|
| Electrocoagulation Unit | Agent-free design reduces sludge production by 60% compared to chemical processes; adjustable voltage/current adapts to water quality fluctuations |
| Flotation & Sludge System | In-situ aeration + automatic slag scraping + bottom sludge discharge, realizing continuous operation without manual cleaning |
| Material & Structure | Carbon steel anti-corrosion + high-molecular PE insulation board, resistant to acid-base corrosion; electrode plates with long service life (≥3 years) |
| Operation Control | Integrated electrical control box, simple operation interface; no professional training required for on-site staff |
3.3 Key Design Features
- Space-Saving: Integrated structure covers only 5 m², suitable for small-scale wastewater treatment sites (e.g., small workshops, laboratories).
- Low Energy Consumption: Working voltage ≤12V, power consumption ≤1.2 kW·h/m³, lower than traditional electrocoagulation equipment (1.5-2.0 kW·h/m³).
- Easy Maintenance: Electrode plates are detachable for cleaning; slag scraping and sludge discharge systems operate automatically, reducing maintenance frequency to once a month.
4. Project Effectiveness Verification
4.1 Pollutant Removal Efficiency (Based on Industry Similar Cases)
| Pollutant | Inlet Concentration (mg/L) | Effluent Concentration (mg/L) | Removal Rate |
|---|---|---|---|
| Suspended Solids (SS) | 200-800 | ≤10 | ≥95% |
| COD (Chemical Oxygen Demand) | 300-1000 | ≤300 | ≥70% |
| Chroma | 100-500 times | ≤50 times | ≥90% |
| Colloidal Substances | 50-200 | ≤5 | ≥95% |
| Heavy Metal Ions (e.g., Cu²⁺, Ni²⁺) | 10-50 | ≤0.5 | ≥99% |
4.2 Operational Performance
- Stability: Continuous operation for 6000 hours without electrode plate passivation or equipment clogging; effluent quality meets GB 8978-1996 Class A discharge standard.
- Adaptability: Adapts to inlet water pH 4-10 and pollutant concentration fluctuations (±20%), with no significant impact on treatment efficiency.
- Sludge Reduction: Sludge production is only 30% of traditional chemical coagulation processes, reducing sludge disposal costs by 50%.
- Operation Convenience: One-key start-stop; parameter adjustment takes ≤5 minutes; daily maintenance takes ≤30 minutes.
4.3 Environmental & Economic Benefits
- Environmental Benefits: No chemical agent addition, avoiding secondary pollution; annual reduction of COD discharge by 2.5-7.2 tons (based on 12 m³/d treatment capacity and 300 working days/year).
- Economic Benefits: Saving chemical agent costs (≈USD 0.3/ton of water) and sludge disposal costs (≈USD 0.2/ton of water); annual operating cost savings of ≈USD 3,650 compared to traditional processes.
5. Case Corresponding Product Quotation Description
5.1 Quotation Overview
| Item | Description | Quantity | Unit Price (USD) | Total Amount (USD) |
|---|---|---|---|---|
| Electrocoagulation Equipment | Model BYECO-0.5; includes electroflocculation rectifier, slag scraping system, sludge discharge system, stainless steel electrical control box, aeration device | 1 set | 8800 | 8800 |
| Total Quotation | – | – | – | 8800 |
5.2 Quotation Terms
| Term Type | Details |
|---|---|
| Validity Period | 20 working days from the date of quotation |
| Payment Terms | Negotiable (reference: 30% advance payment, 70% before shipping) |
| Production Cycle | 15-20 days after the contract takes effect |
| Quotation Inclusion | Tax (excludes freight and on-site installation/commissioning fees) |
| Warranty Period | 1 year from the date of equipment acceptance |
| Country of Origin | China |
| Product Condition | Brand new, factory-tested qualified products |
5.3 Additional Notes
- On-site installation and commissioning services are available at an additional cost; technical personnel can be dispatched to provide free guidance if customers install independently.
- Core spare parts (electrode plates, scraper blades) are provided at cost price for long-term supply; the company guarantees year-round preferential supply of accessories.
- Customization: Equipment treatment capacity (0.3-1.0 m³/h) and material (304 stainless steel optional) can be customized according to actual water quality and site needs.
6. Frequently Asked Questions (FAQ)
6.1 Installation & Commissioning
Q: What are the on-site installation requirements for the equipment?
A: The equipment requires an indoor installation space of ≥5 m², with access to 220V/380V power supply and stable water inlet/drainage pipelines (DN40 interface). The installation slope should be ≤3°, and the ground should bear a load of ≥2 tons/m². We provide detailed installation drawings; commissioning takes 1-2 days to complete after installation.
6.2 Maintenance & Upkeep
Q: How often do the electrode plates need to be replaced or cleaned?
A: The steel electrode plates have a service life of ≥3 years under normal operation. They need to be cleaned once every 3-6 months (depending on water quality) to remove surface scale; the cleaning process takes ≤1 hour and does not require professional tools.
Q: What is the routine maintenance frequency of the equipment?
A: Routine maintenance includes weekly inspection of the slag scraping system and sludge discharge pipeline, monthly cleaning of electrode plates, and quarterly inspection of electrical connections. The entire process is simple, requiring only 1-2 hours of maintenance per month.
6.3 Warranty & After-Sales
Q: What is covered under the 1-year warranty period?
A: Within the warranty period, we provide free repair or replacement for faults caused by design, manufacturing, or material defects, including core components such as the rectifier, electrode plates, slag scraping motor, and control box. Human damage, improper operation, and natural wear are not covered.
Q: How to get after-sales technical support?
A: You can contact us via the after-sales supervision email (info@hellawater.com) or phone. We respond to inquiries within 2 hours and provide remote technical guidance; for on-site maintenance needs, technicians can be dispatched within 48 hours (additional fees apply for non-warranty services). We also conduct annual return visits to understand equipment operation status.
6.4 Operational Cost
Q: What is the estimated daily operating cost of the equipment?
A: The main operating cost is electricity. The power consumption is ≤1.2 kW·h/m³, and the daily electricity cost for 12 m³/d treatment capacity is about USD 1.3 (based on 0.1USD/kW·h electricity price). There is no chemical agent cost, and the annual maintenance cost is about USD 200 (including electrode plate cleaning and spare part replacement), with a total daily operating cost of ≈USD 1.8.
6.5 Safety & Compliance
Q: Is there any safety risk during equipment operation (e.g., electric shock, gas emission)?
A: No. The equipment adopts low-voltage design (≤12V electrolysis voltage) and is equipped with a leakage protection device; the aeration system generates only oxygen and hydrogen micro-bubbles (diluted to safe concentration), with no toxic gas emission. It complies with national electrical safety and environmental protection standards.
Q: Can the treated water be directly reused for production or irrigation?
A: The treated water meets GB 8978-1996 Class A discharge standard; for industrial reuse (e.g., cooling water), it can be used directly after simple filtration. For agricultural irrigation, it needs to meet agricultural water purification requirements (GB5084-2005) through additional pH adjustment or disinfection.